The mudslide in Spanish Fork Canyon last week and the rain have put things a week behind. We were going to pour the basement floor last weekend, but the cement company didn't work on Saturday, so we couldn't get conerete. Also, with the mudslide we couldn't get up to the property to set the grade stakes anyway. The gravel did get put in, so we are ready to go as soon as we can arrange concrete. Logs are scheduled to be there to start stacking on Labor Day Weekend!!